Gully Cleaning Programme

Gully Cleaning Programme FAQ's

Cyclic Gully Maintenance

The Council has approximately 75,000 road gullies which are cleaned on a risk and cyclic basis.

Cyclic Gully Cleaning Frequency

The risk based cyclic gully cleaning is delivered on the following frequencies:

  • Flood location gullies - cleaned 3 times a year
  • Arterial and city centre routes - cleaned 1 time per year
  • Neighbourhood Gully Programme - the cycle frequency is under review and will take into account actual operation timescales for the Neighbourhood Gully Programme delivery
  • Leaf fall locations - will attend over the autumn period to remove leaf fall

It should be noted that the programme dates may be affected by adverse weather and weather warnings. If this occurs, the neighbourhood gully cleaning will be programmed at a later date and the web page updated accordingly.

The Neighbourhood Gully Programme needs residents to comply with the restrictions so that any parked cars are moved to allow access for the large gully vehicles that clean and empty the roadside gullys.

When this programme is on your street, a Temporary Traffic Restriction Notice (TTRNs) will be highlighted as being in place. This means for the times stated please DO NOT park your vehicle on the street.

If your vehicle obstructs the works it will be moved, and you may receive a Parking Charge Notice (PCN). Also, your vehicle may be uplifted to the NRS Vehicle Pound and a charge will be applied to recover your vehicle.

As the TTRO works are being scheduled, we will confirm upcoming neighbourhoods and specific streets on this page. You will also see signage on lampposts and no parking cones on the kerbside, please look out for these and follow the guidance on the highlighted dates.

Neighbourhood Gully Programme

The Neighbourhood Gully Programme aims to prevent flooding by maintaining our drainage network and keeping it running efficiently. It is important that residents move vehicles to allow this work to be carried out and avoid unnecessary delays and costs. See below video for further advice.

Completed Neighbourhood Gully Programme Information

The table below will be updated following completion of each neighbourhood and as the associated follow up programmes are confirmed. (You can view the full table by using the scroll bar at the bottom of the table, or alternatively this can be viewed as a PDF here (PDF, 75 KB)(opens new window)).

Completed Neighbourhood Gully Programme Information
Neighbourhood Gully Programme (NGP)Date NGP CompletedNo. of GulliesNo. of Gullies Satisfactorily Cleaned% of Gullies Satisfactorily CleanedReturn visit (Due to Access/ Severe Weather Issues) Programmed DateNo. of Gullies Req. Follow-Up Repair to Cover/ FrameNo. of Gullies Req. Follow-Up Drainage InvestiagtionRisk and Area-Based Follow-Up Programmed DateComments
Ibrox / KingstonMay-222453174271%-10618  
Hillhead / WoodlandsAug-22101978577%-8212  
Pollokshields EastJun-2244831470%-319  
Tollcross / West ShettlestonJul-222339163770%-11524  
GovanhillJul-2288261770%-7118  
Greater GovanSep-222039157077%-11117  
Hyndland / Dowanhill / Partick EastOct-221416100571%-6028  
Baillieston / GarrowhillDec-222627225986%-9561  
Anniesland / Jordanhill / WhiteinchNov-22134295371%-5627  
Calton / BridgetonMar-231329111784%-226  
Yorkhill / AnderstonFeb-2378361078%-264  
Crookston /South CardonaldFeb-2369755980%-3225  
Langside / BattlefieldApr-23108787881%-5618  
SpringburnApr-231392116884%-9616  
Springboig / BarlanarkMay-231607137886%-9412  
Temple / AnnieslandJun-231561130984%-9322  
Shawlands / StrathbungoJul-2365457788%-6622  
Pollokshaws / MansewoodAug-231258107385%-12416  
Pollokshields WestAug-2393477883%-7512  
KnightswoodJun-231567132585%-9119  
Ruchill / PossilparkNov-231409112880%-1096  
Maryhill Road CorridorNov-23102086485%-804  
North Maryhill / SummerstonNov-231463116379%-1146  
Yoker / ScotstounDec-23115481070%-880  
Greater GorbalsApr-241261108286%-6310  
Broomhill/ Partick WestMar-24110774067% 6437 Access Issues
DrumchapelMar-241557122379% 13249  
CastlemilkApr-241425118680% 12839  
Blackhill/ HogganfieldMay-2438032686% 3012  
Riddrie/ CranhillMay-24114389278% 8918  
Haghill/ CarntyneJun-2496884387% 7026  
DennistounJun-2450635169% 6618 Access Issues
Mount Vernon/ East ShettlestonJun-241540137889% 56103  
Lambhill/ MiltonJul-24127391972% 10463 Vehicle breakdown issues, revisit scheduled.
North Cardonald/ PenileeAug-241637118680% 12962  
Bellahouston/ Craigton/ MossparkAug-2479764481% 4662  
PollokSep-24150482184%Nov-249641  
Barmulloch/Balornock/Ruchazie/GarthamlockNov-2484560872% 

113

29  
Carmunnock/Cathcart/Simshill/CroftfootDec-2470151774% 10316  

 

Future Neighbourhood Gully Programme Schedule

The Neighbourhood Gully Programme for 2024/2025 has been suspended and will recommence after April 2025 and the programme dates for the neighbourhoods listed below will be confirmed in due course.

Reactive Gully maintenance will continue based on risk assessment. 

NeighbourhoodSector
Priesthill / HousehillwoodSouth West
King's Park / Mount FloridaSouth East
Parkhead / DalmarnockNorth East
Kelvindale / KelvinsideNorth West
BlairdardieNorth West
EasterhouseNorth East
Newlands / CathcartSouth West
ToryglenSouth East
Corkerhill / North PollokSouth West
Arden / CarnwadricSouth West
Robroyston / MillerstonNorth East
Sighthill / Roystonhill / GermistonNorth East
South Nitshill / DarnleySouth West

 

 

 

Last modified on 24 December 2024